The High Park Zoo has been closed since October 13, 2026, when construction started on Deer Pen Road. Friends of High Park Zoo has described the zoo as open every day, year-round, so a closure that runs through the winter is new. The closure is one of three changes landing in the park at about the same time. October 31 is the last weekend of the season for the TTC's 203 High Park bus. The City's curb work on Colborne Lodge Drive and West Road also continues through the fall. For anyone who walks over from the north side or up from Swansea, the next few months are mostly about the parts of the park the work leaves alone.
Why Deer Pen Road closed the zoo
Deer Pen Road is the path down to the zoo, across from the Grenadier Café. The City's Animal Display page says the City is improving the road's upper section, which is the main access route to the animals, and that the display stays closed while that work happens.
The work is Phase 2 of the Friends of High Park Zoo master plan. Phase 1 replaced the llama building. According to the group's Phase 2 overview, this phase covers:
- resurfacing the trail
- a storm drainage system built with plant and stone bioswales
- new trees and native planting
- accessibility and safety improvements along the path
The group says the City has already finished the first drainage improvements and has started on what the plans call the Deer Pen Road Promenade.
The two organizations give slightly different reopening dates. The City says spring 2027. Friends of High Park Zoo says early 2027, and its visitor page, updated October 12, also lists the llama pen as closed for the season. The group also expects more partial closures over fall and winter of 2027 and again in 2028 to finish the rest of Phase 2. If that schedule holds, closing the zoo in the quiet months will happen again for at least two more winters.
October 31 is the 203's last weekend run
The 203 bus carries people from High Park Station down West Road and back up Colborne Lodge Drive. Its weekend and holiday service runs from March 15 to October 31. Weekday service already ended on September 4. This Saturday's Halloween service is the last run until spring.
That matters because of the weekend road rules. The City's High Park page says most of the park's roads and parking lots are closed to private vehicles on weekends and holidays. Once the bus stops, there are four ways to reach the middle of the park on a November or December weekend:
- On foot or by bike from the Bloor, Parkside or Ellis Park entrances.
- Drive to the Spring Road lot, which has 21 spaces and stays open every day.
- Drive in from the Queensway to the Children's Garden and Colborne Lodge. That entrance is open to cars seven days a week from October 1 to March 31, but it does not connect through the rest of the park.
- Use Wheel-Trans, which serves the park on weekdays, weekends and holidays all year for registered customers.
On weekdays, private vehicles can still use the park roads, except on statutory holidays.
The curb work skips the busiest winter stretch
The second project going on now is part of the High Park Movement Strategy. City Council approved the strategy in May 2023, and its long-term goal is a car-free High Park. Crews are removing asphalt and realigning curbs in the old parking areas along Colborne Lodge Drive and West Road. The goal is to make the current parallel parking permanent and return the leftover pavement to green space. The City says the work will not reduce or move any existing parking spaces.
The summer plan had this work done by early September. The City's October 2026 update says the scope has changed for operational and technical reasons. The stretches of Colborne Lodge Drive next to the pool, rink and Nature Centre are no longer part of this fall's work. Every other location is still scheduled for fall 2026 and spring 2027.
Those excluded stretches are where much of the park's winter use happens. The rink is the main reason to cross the park after November, and the Nature Centre's programs run through December. Both stay outside this fall's construction zone.
What the April feedback says the roads should become
The curb work is only the first step. A full redesign of Colborne Lodge Drive, West Road and parts of Centre Road is in detailed design from fall 2026 to winter 2027. The City plans to hire a construction team in spring 2027 and build in phases from summer 2027 to summer 2028.
This month the City posted two reports on the spring consultation. The online survey report covers a survey that ran April 1 to 21 and drew 2.7K respondents. The public meeting report covers the April 7 virtual meeting, which 375 members of the public attended. At that meeting, 59% of poll respondents preferred keeping cars, bikes and people separate, and 14% preferred shared spaces. In the survey, support for the proposed safety, accessibility and natural-environment improvements was 81%, 84% and 86%.
The results for each road were less uniform:
| Road area | What was on the table | What the April 2026 survey found |
|---|---|---|
| Spring Road intersection | Option 1 separates pedestrians, cyclists and cars, with one crossing per road north of Spring. Option 2 is a slower, raised, shared intersection with three crossings. | Comments favored Option 1, 28 to 9. 82% liked its dedicated separation. |
| Colborne Lodge Drive by the rink and pool | Option 1 separates bike and car lanes with medians. Option 2 is a raised, pedestrian-priority shared roadway. | 49% opposed Option 2's shared road and 31% supported it. Option 1 also drew more dislikes than preferences in comments, 53 to 33. |
| Colborne Lodge Drive, full length | Option 1 has a two-lane cycle facility with a passing lane. Option 2 has a single protected lane and more parallel parking. | 72% liked the passing lane. 69% preferred Option 1's lower parking count. Comments favored Option 1, 33 to 5. |
| West Road, full length | Option 1 adds more separation. Option 2 is a simpler shared-lane approach. | Close. Option 2 led in comments, 38 to 33. |
The stretch by the rink and pool is the one where neither option clearly won. It is also the stretch the City dropped from this fall's curb work. At a March 2026 meeting, local organizations and permit holders raised concerns about losing parking near the off-leash area, the allotment gardens, the baseball diamonds and the ice rinks. According to the meeting report, a preferred design will be shown at a future virtual meeting. If you want to know when that meeting is scheduled, the City has an update sign-up on the project page.
Where the winter draws are
The rink. The City lists High Park's artificial rink as open November to March, weather permitting. The City's public skating page says artificial rinks usually open in late November. The same page says skating on Grenadier Pond and other open bodies of water is prohibited.
Colborne Lodge. The historic house is open Wednesday to Sunday, 11 a.m. to 4 p.m., with free guided tours at 11:30, 1:30 and 3:30. In winter, the Queensway entrance lets you drive to it on weekends too.
The Grenadier Café. The café's website lists daily hours of 8 a.m. to 7 p.m. all year, except Christmas Day. On weekdays, café parking is reached from Parkside Drive. On weekends, you'll need to walk in.
The High Park Nature Centre. The Nature Centre's late-fall calendar has something on most weekends until the holidays:
| Date | Program | Time and cost |
|---|---|---|
| Sunday, November 8 | Birding walk, ages 16+ | 10 a.m. to noon |
| Sunday, November 8 | Linocut Printmaking Workshop | 1 to 4 p.m., $60 |
| November 15 | Introduction to Silverpoint Drawing | 1 to 4 p.m., $60 |
| November 22 | Linocut Printmaking Workshop | 1 to 4 p.m., $60 |
| Saturday, December 5 | Fall into Winter nature walk, family-friendly | 10 to 11:30 a.m., $10 per person |
| Saturday, December 19 | December Birding Walk, ages 16+ | 10 a.m. to noon, pay what you choose |
| Sunday, December 20 | Christmas Bird Count and Crafting for Kids | 1:30 to 3:30 p.m., $5 per person |
There's also something just outside the park on the west side. The Bloor West Village BIA has listed its 10th annual Santa in the Village for November 21, 10 a.m. to 4 p.m., with the location still to be announced.
When the zoo reopens in 2027, the path down to it should have new trees, better drainage and a more accessible surface. Friends of High Park Zoo has also said to expect more partial closures in the falls and winters of 2027 and 2028.
Our team lives and works around this park, and we watch these projects closely because they affect what life on the nearby streets is like. If you'd like to talk about how the High Park road redesign or the zoo work might affect your plans for a home nearby, the team at Kim Kehoe is glad to walk you through what we're seeing. Contact Us.